Expenses for Dealing with Construction Permits 2013

Homepage > Information > Archive > Expenses for Doing Business in Rostov region 2013 > Expenses for Dealing with Construction Permits 2013

This page summarizesDoing Business2013 data for Rostov-on-Don.

Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.

No.

Procedure

Time to Complete

Associated Costs

1

Request a topographic survey of the land plot at Any commercial organization with corresponding permission from a self-regulating organization

35 days

RUB 77,450 [estimated RUB 10,000-20,000 per 100 m2 of the land plot]

2

Obtain technical conditions for electricity connection at Rostovenergo

30 days

No cost

* 3

Obtain technical conditions for water and sewage services at Vodokanal, OJSC - water utility

30 days

No cost

* 4

Obtain technical conditions for telephone connection at Komstar-Regions, Rostelekom or other companies

14 days

No cost

* 5

Request geological survey of the land plot at Any commercial organization with corresponding permission from a self-regulating organization

60 days

RUB 150,000 [cost estimate for 5-7 borings, 10 meters each (including water analysis), RUB 2,000-3,000 per boring per meter]

6

Obtain development plan of land plot (GPZU) at Architecture and Urban Development Department of Rostov-on-Don City, Municipal Organization

30 days

No cost

7

Obtain construction permit at Architecture and Urban Development Department of Rostov-on-Don City, Municipal Organization

14 days

No cost

8

Obtain compliance certificate of the building with the water and sewage utility at Rostov-on-Don Vodokanal, OJSC - water utility

7 days

No cost

9

Request connection to the water and sewage utility at Rostov-on-Don Vodokanal, OJSC - water utility

4 days

No cost

10

Connect to water services at Rostov-on-Don Vodokanal, OJSC - water utility

28 days

RUB 32,125

11

Obtain compliance certificate of the building with the phone utility at Komstar-Regions, Rostelekom or other companies

3 days

No cost

* 12

Request and connect to telephone services at Komstar-Regions, Rostelekom or other companies

1 day

RUB 4,800

* 13

Sign agreement with the phone utility at Komstar-Regions, Rostelekom or other companies

14 days

No cost

* 14

Conclude agreement on connection services from the phone utility

1 day

No cost

15

Obtain a technical passport of the building at Bureau of technical inventory - federal and municipal

30 days

RUB 12,000

16

Obtain occupancy permit at Architecture and Urban Development Department of Rostov-on-Don City, Municipal Organization

10 days

No cost

17

Obtain cadastral passport of the building at Federal Service of State Registration, Cadastre and Cartography (Rosreestr)

25 days

No cost

18

Registration of the building at the Federal Service of State Registration, Cadastre and Cartography ('Rosreestr')

32 days

RUB 15,000